Ticket #386 (closed defect: fixed)
Incorrect date or task set on monthly schedule
| Reported by: | DavidHB | Owned by: | Joel |
|---|---|---|---|
| Priority: | major | Milestone: | Eraser 6.0.9 |
| Component: | User Interface (UX) | Version: | |
| Keywords: | Cc: | ||
| Processor Architecture: | Blocked By: | ||
| Blocking: | Operating System: |
Description
User john5201 reported as follows:
"After setting up the task to erase my recycle bin on 22nd every month, every day, the schedule will delay 2 days. An example is that on the next day when I check out the schedule, it will be 24th instead of 22nd.".
I have found this bug to be present on version 6.0.8.2273 running on XP and 6.1.0.2276 running on Windows 7. In both cases I found that in fact, there was no obvious consistency between the date set in the dialog and the date of the first run; I have yet to find a way of setting the task so that it reliably executes on the chosen date.
Also, on the Windows 7 machine, when the schedule is edited, both the daily and the monthly radio buttons appear to be checked, with the monthly data greyed out; clicking on the monthly button corrects this.
Blocking
| Id | Summary | Milestone |
|---|---|---|
| #386 | └ Incorrect date or task set on monthly schedule | Eraser 6.0.9 |
Blocked by
| Id | Summary | Milestone |
|---|---|---|
| #386 | └ Incorrect date or task set on monthly schedule | Eraser 6.0.9 |