Incorrect date or task set on monthly schedule

Reported by: DavidHB Owned by: Joel
Priority: major Milestone: Eraser 6.0.9
Component: User Interface (UX) Version:
Keywords: Cc:
Processor Architecture: Blocked By:
Blocking: Operating System:

Description

User john5201 reported as follows:

"After setting up the task to erase my recycle bin on 22nd every month, every day, the schedule will delay 2 days. An example is that on the next day when I check out the schedule, it will be 24th instead of 22nd.".

I have found this bug to be present on version 6.0.8.2273 running on XP and 6.1.0.2276 running on Windows 7. In both cases I found that in fact, there was no obvious consistency between the date set in the dialog and the date of the first run; I have yet to find a way of setting the task so that it reliably executes on the chosen date.

Also, on the Windows 7 machine, when the schedule is edited, both the daily and the monthly radio buttons appear to be checked, with the monthly data greyed out; clicking on the monthly button corrects this.

Blocking

IdSummaryMilestone
#386Incorrect date or task set on monthly scheduleEraser 6.0.9

Blocked by

IdSummaryMilestone
#386Incorrect date or task set on monthly scheduleEraser 6.0.9

Change History

comment:1 Changed 3 years ago by Joel

  • Owner set to Joel
  • Status changed from new to accepted

comment:2 Changed 3 years ago by Joel

  • Status changed from accepted to closed
  • Resolution set to fixed

r2315 should fix this. This fix should be in 6.0.9.